Figure 59 - Isolation Switch Defeater

3. Phase 3 (far right linkage) must be measured for overall travel.

All three phases share the same main actuating shaft but the Phase 3 is the
easiest to measure.

Figure 60 - Isolation Switch Linkage Assembly Location

4. Rest the customer-supplied digital protractor on the bottom of the

isolation switch linkage assembly.

The angle of the linkage must be 180º or slightly higher, with a tolerance
of

0/+6 degrees

.

Closed position

Open position

Isolation Switch
Operating
Handle

Isolation
Switch
Defeater

Isolation Switch Linkage
Assembly (Phase 3)

TIP

If a digital protractor is unavailable, lay a straight edge against the
bottom of the steel lever on the operating shaft to check for parallel
alignment of the red link.