Testing Contactor Operation

1. Connect the appropriate external power supply (120 or 230V AC) to the

test receptacle in the control panel. Turn the selector switch to the TEST
position.

2. Electrically operate the contactor several times. Inspect the armature plate

to verify that it fully contacts the magnetic cores.

3. Turn the selector switch to the OFF position and unplug the test voltage.

4. Remove any metal filings or loose hardware from around the magnetic

cores of the vacuum contactor. The debris is attracted to the coil once it is
energized and could prevent the contactor from closing properly.

ATTENTION: Some control circuit configurations may require control
jumpers to let the contactor close during the test procedure. Do not
jumper any isolation switch contacts such as ISa or ISb (see

Figure 66 on

page 65

for the location of these contacts). Using jumpers for these

contacts may result in equipment damage or injury to personnel.