Rockwell Automation 1512B MV Controllers, 200/400A Two-High Cabinet, Standard and Arc-Resistant Enclosure User Manual

Page 56

Advertising
background image

48

Rockwell Automation Publication 1500-UM055G-EN-P - May 2013

Chapter 5

Maintenance

e. Electrically operate the contactor by pushing the START button on the

unit or at a remote location.

f. Disengage the contactor and move the control switch to the OFF

position. Disconnect the external power supply.

g. Complete the Power Lock-out procedure

4. Open the medium voltage door.

5. Visually inspect that the isolation switch blades fully engage the grounding

pins on the grounding bar. The isolation switch shutters should be closed
(see

Figure 47

).

Figure 47 - Inspecting Isolation Switch in Open Position

See Detail A

Grounding Bar

Isolation Switch Blades

must fully engage

Grounding Pins of

Grounding bar

(Verify for each phase)

Isolation Switch Shutters

must be closed

(Verify for each phase)

Detail A

Grounding Pins

Isolation Switch

Blades in open

position

Viewed from back with components
removed for clarification