Model 227 operation manual – Arc Machines 227 User Manual

Page 75

Advertising
background image

MODEL 227

OPERATION MANUAL

Doc # 740063 Rev E

SECTION VII - CALIBRATION

7.3

ARC VOLTAGE CONTROLLER (AVC) CALIBRATION Cont.


LVL

1

OSC AMPL

.500

IN EXC OUT

0.5 0.5 0.5


PRE-PURGE-POST

5 10

UP-SLOPE-DOWN

1.0 10

ROT--DLY

CW 1.0

STR WFDLY STP
0.0 0.0

RETRACT

0.0

T/MODE

MAN

STLV

25

OSC

OFF

STR AVDLY STP
1.0 0.0

STR/ MODE

TOUCH

RESPONSE

3

2. Prepare the system to strike an arc.

3. Set up a Weld Head on a pipe or plate adequate to withstand 100 amperes without

rotation.

4. Prepare to install the DMM positive lead on to the Guide Ring and the negative

lead to the electrode on the torch. If using RF start instead of Touch Start DO

NOT connect the DMM until after the arc is established.

5. Set WELD/TEST Mode (on RP or Panel) to WELD.

6. Press SEQUENCE START. After the arc is established and meter is connected

the DMM should read 10.0 VDC +/- 0.1 VDC.

7. If out of Tolerance adjust TR-3 on the center plate until the reading is correct.

8. When Arc Voltage is correct press Sequence Stop.


7.4

TORCH OSCILLATION (OSC) AMPLITUDE CALIBRATION

A weld schedule is required for OSC calibration. The first time calibration is

performed this schedule will have to be CREATED. Step 1 (next page) has a place

for writing in the Weld # after it has been created.

NOTE

The adjustment for OSC Calibration is located on the Center Plate under the

computer cover (front panel housing). Turn the Power OFF and unscrew the two

computer cover retaining screws in the front. Lift up on the cover and expose the

center plate. Prop the cover up so it will not fall but so you can still operate the

system. Locate the adjustment screw labeled “TR4” and turn the power back to ON.


7.5