Bore path calculator - power pipe® forged, Bore path calculator - power pipe, Forged – Ditch Witch JT100AT User Manual

Page 93

Advertising
background image

Prepare - 92

JT100/JT100 All Terrain Operator’s Manual

Plan Bore Path

CMW

©

Bore Path Calculator - Power Pipe

®

Forged

Entry pitch, setback, and minimum depth work together with bend limits to determine the bore path. To find
the setback (B) and entry pitch (A) that will take you to the desired minimum depth (D), use the chart
below.

Minimum depth (D)

Entry pitch (A)

Setback (B)

Depth to begin steering (S)

5 ft 3 in (1.52 m)

10.0° / -18%

46 ft 10 in (14.27 m)

2 ft 3 in (0.69 m)

6 ft 0 in (1.83 m)

10.8° / -19%

49 ft 8 in (15.14 m)

2 ft 5 in (0.74 m)

6 ft 8 in (2.03 m)

11.7° / -21%

52 ft 5 in (15.98 m)

2 ft 8 in (0.81 m)

7 ft 6 in (2.29 m)

12.5° / -22%

55 ft 2 in (16.81 m)

2 ft 10 in (0.86 m)

8 ft 4 in (2.54 m)

13.3° / -24%

57 ft 11 in (11.65 m)

3 ft 0 in (0.91 m)

9 ft 2 in (2.79 m)

14.2° / -25%

60 ft 8 in (18.49 m)

3 ft 2 in (0.97 m)

10 ft 1 in (3.07 m)

15° / -27%

63 ft 5 in (19.33 m)

3 ft 4 in (1.02 m)

IMPORTANT: Numbers in table based on 197’ (60 m) minimum bend radius, and beacon housing,
EZ-Connect, transition sub, and half of first drill pipe (L, totaling 14’ 8” [4.47 m]) in the ground before