Table 36: Site Preparation Checklist (continued)

Date

Performed By

For More Information

Item or Task

“AC Power Specifications for EX8200
Switches” on page 109

“DC Power Specifications for EX8200
Switches” on page 110

“Power Requirements for EX8208
Switch Components” on page 111

Power Requirements for EX8216
Switch Components

“Calculating Power Requirements for
an EX8208 Switch” on page 114

Calculating Power Requirements for
an EX8216 Switch

“Calculating the EX8200 Switch
Fiber-Optic Cable Power Budget” on
page 120

“Calculating the EX8200 Switch
Fiber-Optic Cable Power Margin” on
page 121

Calculate the power consumption and
requirements.

Rack or Cabinet

“Rack Requirements for an EX8208
Switch” on page 97

Rack Requirements for an EX8216
Switch

“Cabinet Requirements and
Specifications for an EX8208 Switch”
on page 100

Cabinet Requirements and
Specifications for an EX8216 Switch

Select the type of rack or cabinet and verify that
it meets the minimum requirements for the
installation of the switch.

“Clearance Requirements for Airflow
and Hardware Maintenance for an
EX8208 Switch” on page 101

Clearance Requirements for Airflow
and Hardware Maintenance for an
EX8216 Switch

Plan rack or cabinet location, ensuring the
required space clearances.