Commissioning
During commissioning, system-specific data such as motor parameters, operating
parameters, responses, and parameters for fieldbus communication are defined for the
controller. For Lenze devices this is effected via the so-called codes.
The codes of the controller and for communication are saved non-volatilely as a data set in
the memory module.
Additionally there are codes for diagnostics and monitoring of the nodes.
Parameters of the communication module
6.1
Before initial switch-on
Stop!
Before switching on the standard device with the communication module for
the first time, check the entire wiring for completeness, short circuit, and earth
fault.