Commissioning the CANopen Logic bus

Preparing the restart

Automatic with factory adjustment:

With an automatic restart, a factory adjustment is executed.
– Enter all required parameter values in the Control Configuration under the Service

Data Objects tab.

– Set the checkmark at "Reset Node" in order that the control executes the factory

adjustment. This causes the I/O system to change to the "Lenze System Bus" mode

and remains there.

– Program a "Reset Node" in your program code. Do not use the SDO "Reset Node"

under the Service Data Objects tab. Otherwise the initialisation will be repeated

endlessly.

– After changing the I/O system:

Set the node address and baud rate at the coding switch for the CANopen mode and

then start the control.

8.9.4

Special features of the I/O-System 1000 (EPM-Sxxx)

There are different viable strategies for the I/O system restart:

Automatic:

You want the control to automatically initialise the I/O system after the device has

been replaced.
– Enter all required parameter values in the Control Configuration under the Service

Data Objects tab.

– Go to the Parameters tab and do not set a checkmark at "Reset Node" in order that

the control does not execute a factory adjustment.

– Go to the Parameters tab and set a checkmark at Create all SDOs in order that the

control initialises all parameters.

– After changing the I/O system:

Set the node address and baud rate at the coding switch and then start the control.

Using the »Engineer«:

1. You have implemented the I/O system successfully into the PLC program.
2. You have parameterised some CANopen indexes of the I/O system using the

»Engineer«.

3. You do not want to transmit the parameter setting to the control configuration now,

since you can assume that after a possible device replacement a project planning tool

will be available.
– Operate the I/O system in CANopen mode.
– Go to the Parameters tab and do not set a checkmark at "Reset Node" in order that

the control does not execute a factory adjustment.

– Save the »Engineer« project near the machine.
– After changing the I/O system:

Set the node address and baud rate at the coding switch and transmit the archived

parameter setting to the I/O system. Then start the control.