DeviceNet Node Commissioning 3-5

3. Select the E1 Plus Overload Relay located at node 63.

4. Select

OK. The Node Commissioning screen shows Current Device

Settings entries completed. It will also provide the current network baud
rate in the New E1 Plus Overload Relay Settings area. Do not change
the baud rate setting, unless you are sure it must be changed.

5. Type the node address that you want in the New Device Settings

section. In this example, the new node address is 5.

6. To apply the new node address, select

Apply.

7. When the new node address has been successfully applied, the Current

Device Settings section of the window is updated (see the example
below). If an error occurs, check to see if the device is properly powered
up and connected to the network.

Figure 3.5 Node Commissioning Confirmation Window

8. To exit the node commissioning tool, select

Close.

9. To update RSNetWorx and verify that the node address is set correctly,

select

Single Pass Browse from the Network menu.