DeviceNet Node Commissioning 3-5
3. Select the E1 Plus Overload Relay located at node 63.
4. Select
OK. The Node Commissioning screen shows Current Device
Settings entries completed. It will also provide the current network baud
rate in the New E1 Plus Overload Relay Settings area. Do not change
the baud rate setting, unless you are sure it must be changed.
5. Type the node address that you want in the New Device Settings
section. In this example, the new node address is 5.
6. To apply the new node address, select
Apply.
7. When the new node address has been successfully applied, the Current
Device Settings section of the window is updated (see the example
below). If an error occurs, check to see if the device is properly powered
up and connected to the network.
Figure 3.5 Node Commissioning Confirmation Window
8. To exit the node commissioning tool, select
Close.
9. To update RSNetWorx and verify that the node address is set correctly,
select
Single Pass Browse from the Network menu.