Chapter 10 Glossary of Fields

176

Rockwell Automation Publication RPTEXP-UM001H-EN-P-June 2014

being produced and is measured in units of seconds per part. The
calculation for this field is:
Throughput = (TotalParts x IdealCycleTime) / Running Time.

Time in Event

The total time (HH:MM:SS.mmm) in the reporting period during
which an event or state was occurring.

Total Duration

The total time (HH:MM:SS.mmm) in the reporting period during
which an event or state was occurring.

Total Parts

The total number of parts produced.

Uptime

A ratio of running time to available time. Uptime is the time a work
cell is expected to be running and producing product.

Uptime %

The percentage of available time that the machine was actually

running. The calculation for this field is:
Uptime % = RunningTime/AvailableTime.

Work Cell

A level of the plant model (which is constructed by enterprise, site,
area, line, and then work cell).