Powering up after installation is complete, 2 powering up after installation is complete – Rockwell Automation GV3000/SE AC Bookshelf Drive Hardware Ref, Installation, and Troubleshooting User Manual

Page 70

Advertising
background image

9-2

GV3000/SE AC Bookshelf Drive Hardware Reference, Version 6.06

Step 10. Check that the incoming power is rated correctly.
Step 11. Check the motor installation and length of motor leads.
Step 12. Disconnect any power correction capacitors connected between the drive

and the motor.

Step 13. Check that the rating of the transformer (if used) matches the drive

requirements and is connected properly.

Step 14. Verify that a properly-sized ground wire is installed and a suitable earth

ground is used. Check for and eliminate any grounds between the motor

frame and the motor power leads. Verify that all ground leads are unbroken.

Step 15. Uncouple the motor from any driven machinery to initially start the drive.

9.2 Powering Up After Installation Is Complete

Use the following procedure to verify that the drive is installed correctly and is

receiving the proper line voltage:
Step 1. Turn the drive’s input power disconnect to the On position.
Step 2. Apply power to the drive.
Step 3. Follow the start-up procedure in the GV3000/SE Bookshelf Drive Software

Start-Up and Reference manual.