2 Connecting to CC-Link

Connecting to the Field Network

To connect to the master device or network controller on the field network using a

multidrop connection, or to connect other slave devices, connect a communication cable

that supports each field network to the field network connector.

Preparing the communication cable

Use a communication cable dedicated for CC-Link (Ver. 1.10 or higher).

1

Remove the sheath (outer insulation) from the cable.

Carefully remove about 50 mm from the end of the dedicated cable so as not to

damage the braided shield wires.

2

Prepare the shield.

Carefully unravel the braided shield wires. Inside the shield is a single exposed

drain wire (twisted or loose). Twist this with the unraveled shield wire and cover it

with an insulation tube.

3

Strip the insulation from the signal lines.

Being careful not to damage the signal lines, remove the aluminum polyester

laminated tape and filling, and strip about 8 mm from each signal line.

Twist the exposed conductor strands to keep them together.

Approx. 50 mm

Shield (braided shield wire)

Sheath (outer insulation)

Aluminum polyester laminated tape

Twisted shield wire

Insulation tube

Approx. 8 mm

Twist conductor strands together