Installation check – Nortec NH-EL Series User Manual

Page 42

Advertising
background image

39 | Start Up

Steam Line

- Adequate slope

- No restrictions

- No kinks (hose)

- Condensate traps

on long runs

P Trap

.

.

with 12 in

(30 cm) min drop
.

Fused

Disconnect

Correct

voltage /

amps /

phase

per spec

label.

On/Off Controls

(Air Proving)

in series between

terminal 1 and 2

Min 10 ft (3 m)

Control
- Wired to terminal 4.
- On/Off in series between
terminal 1 and 2.
- In return duct or location
which represents humidified
space (no drafts, not by
door, not by diffuser).

Air
gap

1/2 in line min
30-80 PSI

Not plastic drain,
Not to sink.

High Limit
- Wired to terminal 5
- On/Off in series
between terminal
1 and 2

Mounting

- Unit level

- Screws into

structural member

- L Bracket on top

Spec label

Calculated absorption distance

to any obstruction or 8 - 10 ft

(2.4 - 3 m) if unknown.

2 x duct height

from fan or

transition

SPACE

SPACE

Installation Check

Before turning on power to the NH-EL, inspect the installation to ensure that it was carried out
correctly. Refer to Figure 35: Installation Check, to the NH-EL Pre-Start Up Checklist on page
46, and to the chapter on Installation that starts on page 9.








Figure 35: Installation Check