Internal Electrical Connections

SMA Solar Technology AG

48

SC20_25_35-IEN094521

Installation Guide

5.9.2 Connecting Team Cables for Sunny Central 200 / 250 with

the "Protection against Chemically Active Substances" Option

Team cabling must be implemented for the team leader and the team device.
Team cabling is pre-installed in the AC cabinet. The team cables are in the AC cabinet. The connection
terminals for team cabling are in the DC cabinet.
The following diagram shows the position of the connection terminals for team cabling in the
Sunny Central 250.

A

Team cable connection point

Position of the connection terminals for team cabling
The exact position of the connection terminals for team cabling can be determined with the
help of the equipment identifier and the circuit diagram enclosed.