(b) Secure the AC CORD-B cables to the FG, NEUTRAL and LINE terminals as shown in

Figure 003-

12

. The 3P AC Power Cable and the FG Cable are pre-installed with the BASE.

Figure 003-12 Screwing the AC CORD-B to the Terminals

NAP 200-003

Sheet 14/37

Installation of Main Equipment

FG

NEUTRAL

LINE

BASE

3P AC POWER CABLE

TO 120/240 V AC
SOURCE POWER

AC POWER
KNOCK OUT HOLE

(PROVIDED WITH BASE)

FG CABLE
(PROVIDED WITH BASE)

PIM

AC CORD-B
TO PZ-PW86 IN PIM
(PROVIDED WITH PIM)

PUSH
PULL

: INSERT THE AC CORD
: FIXED THE AC CORD

CORD BUSH
(PROVIDED WITH BASE)

SUPPLEMENTARY GROUND
(TO COLD WATER PIPE, ETC.)