Installation – Elmo Rietschle 2FC4...-1CB User Manual

Page 23

Advertising
background image

Installation

5

© Gardner Denver Deutschland GmbH

23

/

74

05.2014 · 610.00260.40.000

Power connection of size D

Power connection BG D

1. Unscrew the four screws from the housing cover of the drive controller and

remove the cover.

2. Run the mains cable through the threaded cable gland and connect the

phases with the contacts L1, L2, L3 for 400 V and the buried cable with the
PE contact on the terminal. The threaded cable gland provides cable relief,
the PE connection line must be connected as a leading contact (significantly
longer)!

When connecting a braking resistor to an optional brake module, shielded
and double-insulated cables must be used.

3 ~ 400 V terminal assignment X1

Terminal no.

Designation

(Terminal) assignment

1

L1

Mains phase 1

2

L2

Mains phase 2

3

L3

Mains phase 3

4

PE

Buried cable

DC supply 250 to 750 V terminal assignment X1

Terminal no.

Designation

(Terminal) assignment

1

L1

DC network (+) (565V)

2

L2

Not assigned.

3

L3

DC network (-)

4

PE

Buried cable

Motor terminal assignment X4

Terminal no.

Designation

(Terminal) assignment

1

PE

Buried cable

2

U

Motor phase 1

3

V

Motor phase 2

4

W

Motor phase 3