Installing sneak fuse panels – Avaya 03-300686 User Manual

Page 57

Advertising
background image

Installing sneak current and off premise protection

Issue 3 January 2008

57

Installing sneak fuse panels

For general information, see

Installing sneak current and off premise protection

on page 54.

Figure 26: Model 507B sneak fuse panel

on page 55, or equivalent, is recommended for sneak

current protection. The panel contains two 25-pair connectors, fuse removal tool, and fifty
220029 sneak fuses (and two spares). See

Table 6: Sneak fuse connector pinout

on page 56

for pinout data.
To install sneak fuse panels:

1. Locate the 507B near the network interface or the main distribution frame (MDF).

2. Hold the panel against the mounting surface and mark the mounting screw locations. Drill

pilot holes at the marked locations and partially install a locally obtained #12 x 3/4-inch
screw into the two bottom mounting slots.

3. Slide the sneak fuse panel onto the mounting screws and tighten the screws securely.

4. Install a locally obtained #12 x 3/4-inch screw into the top two mounting slots and tighten

securely.

5. Repeat the procedure for each sneak fuse panel.

6. Secure the B25A cable to the panel with the captive screw on the connector and a supplied

cable tie.

45/20

20

46/21

21

47/22

22

48/23

23

49/34

24

50/25

25

Table 6: Sneak fuse connector pinout (continued)

Connector
pin numbers

Pair/fuse
number

2 of 2

Advertising