4.4 10 mm access port prepared to be finalized by the user (UF V (E2.1), UF V-

UL (E2.1))

The UF V (E2.1) is equipped with an access port to be finalized by the user for cables with a diameter of

up to 10 mm. When finalizing this access port the freezer should be approx. at room temperature.

CAUTION

Works inside the UF V with low inside temperature.
Danger of injury by freezing on.

Turn off the freezer prior to finalizing the access port an let it warm up until approx.

room temperature.

To finalize the access port proceed as follows:

Break out the pre-punched rectangle in the rear wall (Figure 20) with suitable pliers

Break out the pre-punched rectangle in the inner chamber (Figure 21) with suitable pliers

Use a screwdriver to pierce the PU foam insulation horizontally from the inside

Pass the desired cables through the port

Use the sealing kit (art. no. 8009-0815) for sealing. The included insulation tube is to close the

remaining free space after passing the cables. Thoroughly seal both openings of the port with the

sealant. This avoids the entry of humidity from the ambient air into the insulation.