Piping checklists, General piping checklist – Goulds Pumps IC - IOM User Manual
Page 30
1
7
6
2
3
4
5
1.
Baseplate
2.
Shims or wedges
3.
Grout
4.
Foundation
5.
Sleeve
6.
Dam
7.
Bolt
6. Fill the remainder of the baseplate with grout, and allow the grout to set for at least 48 hours.
1
5
4
2
3
1.
Baseplate
2.
Grout
3.
Foundation
4.
Dam
5.
Bolt
7. Remove the leveling jackscrews after the grout hardens in order to remove any stress points.
8. Tighten the foundation bolts.
9. Make sure that treatment of the concrete is in accordance with DIN 1045.
Piping checklists
General piping checklist
Precautions
CAUTION:
• Never draw piping into place by using force at the flanged connections of the pump. This can impose
dangerous strains on the unit and cause misalignment between the pump and driver. Pipe strain
adversely affects the operation of the pump, which results in physical injury and damage to the
equipment.
• Vary the capacity with the regulating valve in the discharge line. Never throttle the flow from the
suction side. This action can result in decreased performance, unexpected heat generation, and
equipment damage.
NOTICE:
Flange loads from the piping system, including those from the thermal expansion of the piping, must not
exceed the limits of the pump. Casing deformation can result in contact with rotating parts, which can
result in excess heat generation, sparks, and premature failure.
Installation
28
Model IC, ICI, ICH, ICIH Installation, Operation, and Maintenance Manual