Commissioning

Initial switch-on

42

L

EDS84AYCEC EN 3.0 - 09/2012

Initial switch-on and diagnosing

1. Switch on the controller and check whether it is ready for operation using the

diagnostic LEDs of the communication module.
• Red diagnostic LEDs must not be on.
• The following signalling should be visible:

2. If not already done, load the EPL configuration into the controller.
3. Repeat steps 1 and 2 for all EPL nodes.
4. Start network.

The network starts automatically if you set the managing node last.
Otherwise there are two options:
• Switch off the network nodes and switch them on together or
• execute a fault reset on the managing node (EPL address 240).

5. Check the EPL network again using the diagnostic LEDs of the communication

module.
The following signalling should be visible:

LED

Colour

Status

Meaning

MS

Green

On

Module Status

Module status displays ( 54)

DE

-

Off

Device Error

X251

Green

On

LED is lit if a connection to the node has been established.

Status displays at the RJ45 sockets (X251, X252) ( 56)

X252

Green

On

LED

Colour

Status

Meaning

MS

Green

On

Module Status

Module status displays ( 54)

ME

-

Off

Module Error

BE

-

Off

Bus Error

DE

-

Off

Device Error

BS

Green

On

Bus Status

Fieldbus status displays ( 55)

X251

Green

On

LED is lit if a connection to the node has been established.

Status displays at the RJ45 sockets (X251, X252) ( 56)