Commissioning

6.1

Before initial switch-on

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

6

Commissioning

During commissioning, plant-specific data such as motor parameters, operating parameters,

responses, and parameters for fieldbus communication are defined for the controller. Lenze devices

use codes for this purpose.
The codes of the controller and for communication are saved to the memory module in a non-

volatile data set.
In addition, there are codes for diagnosing and monitoring the stations.

6.1

Before initial switch-on

Note!

When parameterising the communication module, please observe that the code number

depends on the slot of the Servo Drive 9400 in which the communication module has

been inserted.
The first two digits of the code number indicate the slot:

• C13nnn for slot MXI1



Parameters of the communication module for slot MXI1

( 93)

• C14nnn for slot MXI2



Parameters of the communication module for slot MXI2

( 102)

You also have to set the

Communication-relevant parameters of the standard device

( 91)

.

Stop!

Before switching on the controller for the first time, check ...

• the entire wiring for completeness, short circuit and earth fault:
• whether the bus system is terminated through a bus terminating resistor at the first

and last physical bus station.



Activating the bus terminating resistor

( 25)