6 commissioning, 1 before switching on, 2 commissioning steps – Lenze E82ZAFVC010 User Manual

Page 29: Commissioning, Before switching on, Commissioning steps

Advertising
background image

Commissioning

Before switching on

6

l

29

EDS82ZAFVCxxx EN 4.0

6

Commissioning

During commissioning, system−dependent data as e.g. motor parameters, operating
parameters, responses and parameters for fieldbus communication are selected for the
controller.

In Lenze devices, this is done via codes. The codes are stored in numerically ascending order
in the Lenze controllers and in the plugged−in communication/function modules.

In addition to these configuration codes, there are codes for diagnosing and monitoring
the bus devices.

6.1

Before switching on

(

Stop!

Before you switch on the basic device with the function module for the first
time, check

ƒ

the entire wiring for completeness, short circuit and earth fault.

ƒ

whether the bus system is terminated by terminating resistors at the first
and last bus station.

6.2

Commissioning steps

)

Note!

ƒ

For software version < 3.5 of the basic devices:
If you keep to the switch−on sequence decribed in the following table (basic
device must be switched on before the function module), a communication
error is indicated by the basic device.
This error message can be
– avoided by switching on the function module first and then the basic

device.

– automatically deleted by activating the function "Automatic trip reset" via

code C1566 (see chapter "Code table").

ƒ

For software versions

³ 3.5 of the basic devices:

Keep to the switch−on sequence described in the commissioning steps (table
below).