Pre-Commissioning

Pre-Commissioning
Responsibilities

Rockwell Automation manages the start-up service for each installed drive at the
customer’s site, but there are a number of tasks the customer or its representatives
must complete before scheduling Rockwell Automation personnel for drive
commissioning.

Review this information prior to commissioning the drive as a reference for drive
line-up commissioning. Record the information in the data sheets provided;
these are useful during future maintenance and troubleshooting exercises.

Inspection and Verification

Before the drive commissioning occurs, Rockwell Automation recommends that
the customer arranges a pre-installation meeting to review:

a. the start-up plan
b. the start-up schedule
c. the drive(s) installation requirements
d. the pre-commissioning checklist

Customer personnel must be on-site to participate in the system start-up
procedures.

See

Safety and Codes on page 41

.

ATTENTION: Perform the pre-commissioning tasks in the order listed in this
chapter. Failure to do so may result in equipment failure or personal injury.

IMPORTANT

Rockwell Automation requests a minimum of four weeks’ notice to schedule
each start-up.

ATTENTION: The CMOS devices used on the control circuit boards are
susceptible to damage or destruction by static charges. Personnel working near
static sensitive devices must be appropriately grounded.