To perform the RAM Test

This tests the validity of the terminal’s RAM memory. The Historical
Event Stack, message Queue and internal buffer information are
stored in RAM.

1. Highlight RAM Test and press

to run the test.

The result of the test is displayed at once.

RAM Test

Test Passed

If the test fails, see Page B–4.

2. Press the Ack

key to return to the Self Tests submenu.

3. Press Ack

again to return to the FPE menu.

To perform the Battery Test

The terminal battery supplies power to the Real Time Clock and
memory chips so that time, system parameters and HE Stack
information are maintained while power is disconnected from the
terminal.

1. Highlight Battery Test and press

to run the test.

The result of the test is displayed at once.

Battery Test

Test Passed

If the test fails, see Page B–4.

2. Press the Ack

key to return to the Self Tests submenu.

3. Press Ack

again to return to the FPE menu.