GE Industrial Solutions GPS2436 User Manual

Page 76

Advertising
background image

Galaxy Power System GPS2436

Issue 1 August 2012

76

Step

Action for Voltage Calibration

1.

Using the Meter Calibration Menus, reset the plant voltage reading by

selecting RESET VOLTAGE. Press the Enter key to reset the voltage. This

will remove any pre-existing user calibrated values if they exist.

2.

Wait at least 5 seconds and press the ESCAPE key.

3.

Select CALIBRATE VOLTAGE. Use the Arrows, and UP/DOWN keys to

calibrate the system voltage. Press ENTER to save.

NOTE:

The controller will not allow changes greater than +/- 0.5V of the

displayed voltage.

4.

Press the <ESCAPE> key until the default screen is displayed. Verify that

the plant voltage reading now agrees with the calibrated DVM.

NOTE:

The DVM reading will be the one to change since Rectifier Manager will

adjust rectifier outputs as necessary per the calibration performed.

Step

Action for Current Calibration

NOTE:

The following procedure is applicable only in plants with Load shunts in

a plant configured for “Centralized Architecture.”

1.

Using a calibrated DVM, measure the plant load from the sense