Basic Installation and User’s Guide for the Millennium II Controller

Issue 3 January 2008

100

Config Auto Restart to:

Enabled if Millennium was 1
Disabled if Millennium was 0

SW202-6 Critical

=

Major

Relays

Using the front panel, go to:

MenuÆConfigÆSystem Settings

Config Crit=Major to:

Enabled if Millennium was 1
Disabled if Millennium was 0

SW202-5

Alarm Test

Using the front panel, go to:

MenuÆConfigÆAlarm Test

Config Test to:

Enabled if Millennium was 1
Disabled if Millennium was 0

SW202-4

HVSD during Alarm
Test

Using the front panel, go to:

MenuÆConfigÆAlarm Test

Config HV Shutdown to:

Enabled if Millennium was 1
Disabled if Millennium was 0

SW202-3

Boost Mode

Using the front panel, go to:

MenuÆConfigÆRect Boost

Config Enable to:

Enabled if Millennium was 1
Disabled if Millennium was 0

SW202-2 External

Timed

Boost

Using the front panel, go to:

MenuÆConfigÆRect Boost

Config Timed to:

Enabled if Millennium was 1
Disabled if Millennium was 0

SW202-1

Password Reset for
Indep Modem

Not Applicable for Millennium II

IntelligentController (BSJ) Dip Switch Settings

Millennium

Switch

Position

Description

Millennium II Setting

SW203-8 Remote

Rectifier

in

Standby

Set SW202-4 to:

0 if Millennium was 0
1 if Millennium was 1

SW203-7 Remote

Rectifier

Turn On

Using the front panel, go to:

MenuÆConfigÆPlant

Config Remote On to:

Enabled if Millennium was 1
Disabled if Millennium was 0

SW203-6 Full

Access

through

Local Port

Using the front panel, go to:
MenuÆConfigÆComm PortsÆLocal Port

Config Write to: