Basic Installation and User’s Guide for the Millennium II Controller

Issue 3 January 2008

103

3.

Connect Serial Rectifier Cable

The RJ45 connector is located at top of the MCR1 board and is labeled
P9.

(see Figure 6-11)

Step Action

a.

Locate P9 (Not to be confused with P7-Aux)

b.

Using the existing serial cable, connect to P9.

4.

Removing the Forced Contactor Conditions

If Battery and Load contactors are in the system, contactor control boards
should have be configured so that they did not OPEN during the controller
replacement.
NOTE: Contactors may have always been in the FORCED state per customer
requirements. If no changes were made to the Contactor States in the
“Securing Contactors” section, then DO NOT change the switch positions.
To return contactors to their normal state, place SW300 in the position as
shown figure 6-2 and 6-3.

Contactor Type

Control Board and

Switch

For Millennium II

Control, Change to

Load

EBV – SW300

DOWN

Battery

BJN – SW300

DOWN for ½ height

cabinets

UP for full height

cabinets