4 new installations – GE Industrial Solutions Millennium II Controller J85501P-1 User Manual

Page 21

Advertising
background image

Basic Installation and User’s Guide for the Millennium II Controller

Issue 3 January 2008

21

4 New Installations

The Millennium II is factory pre-installed and pre-configured with industry standard
defaults for thresholds and feature operability in GPS cabinet applications. In addition,
customer specific default controller settings may be available upon request. This section
provides:

Preparation and Precautions

Procedures for the proper addition of optional packs

Input and output wiring to the controller and the installation and
wiring of optional features

Controller default configuration information such as alarm severity
and description, system voltage, shunt information

Controller configuration information

Preparation

The following
Installation
procedures should
be performed
AFTER:

• All the equipment frames (initial and supplemental bays, free-

standing rectifiers, etc.) are anchored in place.

• The battery stands have been erected and the batteries installed.

• The overhead cable racks have been installed and the power

cables have been run and terminated.

• The plant’s charge and discharge bus bar assemblies have been

installed.

But BEFORE:

• Connecting the batteries to the plant charge and discharge bus

bars or turning up the plant rectifiers.

Precautions
Observe ESD protection while installing circuit packs.
Wear grounded antistatic wrist straps when handling all circuit packs. The wrist strap
must contact the skin and is not to be worn over clothing.
Never hand a circuit pack from a grounded to a non-grounded person or vice-versa.

Advertising