Performance Verification

Performance Verification Test

Performance Verification Test

The following verification procedure will verify the Agilent 85330 system in
two parts. The first part will verify the operation of the multiple channel
controller to make sure that it is controlling the switches and the receiver
correctly. The second part will check the switch’s RF performance and to
make sure that they are switching correctly.

Setting Up the Equipment

85330 System

Connect the 85330 system to the switch control unit using the correct local
control cable. This should be set up the same way that the 85330A system is
used in the measurement system (Agilent 85301B/C). Do not connect the
Switch Control Units (SCU) to their switches at this time. Do not connect
the 85330A to any other instruments in the measurement system. An
example of a setup is shown in

Figure 2-1

. Do not turn ON the 85330A at

this time.

Figure 2-1

An Example Performance Verification Setup