Installing the new telco alarms module, 7 replacing the power distribution board, Figure 63 – Kontron CG2100 Carrier Grade Server User Manual

Page 70

Advertising
background image


69

Figure 63. Disconnecting the TAM Cables

6.

Remove the TAM board from the chassis by lifting it off of the two standoffs on the

left side of the board. (Figure 62 “B” and “C”)

Installing the New Telco Alarms Module

1.

Align the left side of the TAM board with the two standoffs on the floor of the

chassis where the black protective cover is mounted and gently push the board to
secure it on the standoffs. (Figure 62, “B”)

2.

Fasten the retaining screw at the right of the TAM board to hold the board in

place. (“A”)

3.

Replace the front panel board if you removed it or slid it out to work on the

LED/switch board installation. For instructions, see “Installing the New Front
Panel Board” in Section
5.4.

4.

Connect the alarms cable from the FP board to the TAM board. (Figure 63, “A”)

5.

Connect the alarms cable from the rear of the chassis to the TAM board. (“B”)

6.

Re-fasten the black protective cover over the FP board.

7.

If this is the last task you are performing inside the server chassis, replace the

front chassis cover, reconnect the power cord(s), and reconnect any external
devices.

5.7

Replacing the Power Distribution Board

The power distribution board (PDB) routes power from the power supply module(s) to the
rest of the server through an integral wiring harness. For safety, ventilation, and
heat dissipation, the PDB has a black plastic cover around it, which also provides
guides for some of the cables.

To replace the PDB, you must first remove the following components:

Advertising