JT60/JT60 All Terrain Operator’s Manual

Prepare - 63

Inspect Site

Select Start and End Points

Select one end to use as a starting point. Consider the following when selecting a starting point:

Slope

Always level machine before drilling. Fluid system should be parked on a level site. Consider how slope
will affect drilling unit setup, bending pipe, and fluid flow out of hole.

Traffic

Vehicle and pedestrian traffic must be a safe distance from drilling equipment. Allow at least 10’ (3 m)
buffer zone around equipment.

Space

Check that starting and ending points allow enough space for gradual pipe bending. See “Minimum
Setback” on page 72.

Check that there is enough space to work and to set up electric strike system.

Comfort

Consider shade, wind, fumes, and other site features.

Drill downhill when possible so fluid will flow away from drilling unit.