Lift, Pipe box lifting procedure, Jt60/jt60 all terrain operator’s manual – Ditch Witch JT60AT User Manual

Page 88

Advertising
background image

Transport - 88

JT60/JT60 All Terrain Operator’s Manual

Lift

Lift

This machine is not configured for lifting. If the machine must be lifted, load machine into a container or
onto a platform appropriate for lifting. See “Specifications” for weight of machine.

Pipe Box Lifting Procedure

Pipe box lifting points are identified by lifting decals. Lifting at other points is
unsafe and can damage equipment.

Ensure that proper remove/install procedure is followed. See “Remove/
Install Pipe Box” on page 147.

Use crane capable of supporting the equipment's
size and weight. See “Specifications” on page 207
or measure and weigh equipment before lifting.

Crushing weight could cause death or serious injury. Use

proper procedures and equipment or stay away.

IMPORTANT: Lift only one box of pipe at a
time.

Advertising
This manual is related to the following products: