Jt60/jt60 all terrain operator’s manual – Ditch Witch JT60AT User Manual

Page 75

Advertising
background image

JT60/JT60 All Terrain Operator’s Manual

Prepare - 75

Plan Bore Path

JT60 Power Pipe AT

Minimum depth (D)

Entry pitch (A)

Setback (B)

Depth to begin steering (S)

5’ 4”

18”/10.0°

47’ 12”

2’ 3”

6’ 2”

19%/11.0°

51’ 6”

2’ 5”

7’ 2”

21%/12.0°

54’ 11”

2’ 8”

8’1”

23%/13.0°

58’ 5”

2’ 10”

9’ 2”

25%/14.0°

61’ 10”

3’ 1”

10’ 3”

27%/15.0°

65’ 3”

3’ 4”

11’ 5”

29%/16.0°

68’ 7”

3’ 6”

IMPORTANT: Numbers in table based on 168.7’ (51.4 m) minimum bend radius, beacon housing, EZ-
Connect, connector, transition sub, and 1/3 of first drill pipe (L, totaling 12’ 10” [3.9 m]) in the ground
before steering.