Test 28 – check 23 and 15bwiring/connections – Generac Power Systems 8 kW LP User Manual

Page 78

Advertising
background image

b. Actuate the operating lever down to move the

load contacts against the standby contacts, i.e.,
load connected to the Standby source.

6. Repeat Step 5 several times. As the transfer switch

operating lever is moved slight force should be needed

until the lever reaches its center position. As the lever

moves past its center position, an over-center spring

should snap the moveable load contacts against the

stationary STANDBY or UTILITY contacts.

7. Finally, actuate the main contacts to their UTILITY power

source side, i.e., load contacts against the UTILITY contacts

(upward movement of the operating lever).

RESULTS:

1. If there is no evidence of binding, sticking, or excessive

force required, refer back to flow chart.

2. If evidence of sticking, binding, excessive force required

to move main contacts, find cause of binding or sticking

and repair or replace damaged part(s).

teSt 28 – check 23 and 15B WirinG/

connectionS

DISCUSSION:
An open circuit in the transfer switch control wir-
ing can prevent a transfer action from occurring.
Battery voltage +12 VDC is supplied on Wire 15B.
This DC voltage is supplied to the transfer relay (TR)
at Terminal Location “A”. The opposite side of the
transfer relay (TR) coil (Terminal B) is connected
to Wire 23. Positive 12 VDC is present on this also.
Circuit board action will allow current to flow through
the circuit and the (TR) is energized.

PROCEDURE/ RESULTS:
Refer to Figure 3.

1. Remove transfer relay mounting screws so that contact

movement can be visually observed.

2. Set the generator AUTO-OFF-MANUAL switch to the

AUTO position. Turn off utility power supply to the

transfer switch, simulating a utility failure. Visually

watch the transfer relay for contact movement. The

relay should be energized and contact movement seen

approximately 10 seconds after the generator starts.

a. If the transfer relay energizes, discontinue

testing. Refer to flow chart.

b. If the transfer relay does not energize, continue

to Step 3.

3. Set the generator AUTO-OFF-MANUAL switch to the

OFF position.

4. Remove the battery charger fuse (F3) from the transfer

switch to disable the battery charge circuit.

*

caution: after removing the fuse from the bat-

tery charger, wait 5 minutes before proceeding.

5. Set VOM to measure DC voltage.
6. Connect the negative (-) test lead to Wire 0 at the termi-

nal strip in the transfer switch. Connect the positive (+)

test lead to Wire 15B at the terminal strip in the transfer

switch.

a. If voltage is present, proceed to Step 7.

b. If voltage is not present proceed to Step 17.

7. Connect the positive (+) test lead to Wire 23 at the termi-

nal strip in the transfer switch.

a. If voltage is present, proceed to Step 8.

b. If voltage is not present, set VOM to measure

resistance.

c. Remove Wire 23 and Wire 15B going to the

transfer relay from the transfer switch terminal
strip. Connect the meter test leads across Wire
23 and Wire 15B.

d. Transfer coil resistance of approximately 115

ohms should be measured.

e. If coil resistance is not measured, remove

Wire 23 and Wire 15B from the transfer relay.
Measure across Terminal A and Terminal B of
the transfer relay.

f. If coil resistance is measured repair or replace

Wire 23 or Wire 15B between the terminal strip
and the transfer relay.

g. If coil resistance is not measured replace trans-

fer relay and retest.

8. Connect the negative (-) test lead to the ground lug in

the generator control panel. Connect the positive (+)

test lead to Wire 23 in the generator control panel at the

terminal strip.

a. If voltage is present, proceed to Step 9.

b. If voltage is not present, repair wiring between

transfer switch and generator control panel.

9. Remove the J2 connector from the circuit board.
10. Set VOM to measure resistance.
11. Connect one meter test lead to Wire 23 Pin Location

J2-5. Connect the other meter test lead to Wire 15B

Pin Location J2-8. Approximately 115 ohms should be

measured. (see Figures 4 through 7, Section 4.1).

a. If approximately 115 ohms is measured proceed

to Step 12.

b. If infinity or an open is measured, repair Wire 23

between PCB Connector J2 and the generator
terminal strip.

c. If resistance is not within specification, go to

Test 29 – Test Transfer Relay.

12. Reconnect the J2 connector to the PCB.

Page 76

Part 3

TRANSFER SWITCH

sEctioN 3.4

DiaGNostic tEsts