Test 35 – check n1 and n2 wiring, Test 36 – check n1 and n2 voltage – Generac Power Systems 8 kW LP User Manual

Page 85

Advertising
background image

PROCEDURE:

1. On the generator panel, set the AUTO-OFF-MANUAL

switch to OFF.

2. Turn off the utility power supply to the transfer switch,

using whatever means provided.

3. Remove fuses F1 and F2 from the fuse holder (see

Figure 8).

4. Inspect and test fuses for blown condition. With a VOM

set to measure resistance, CONTINUITY should be

measured across the fuse.

BLACK

T1

N1A

N2A

N1

N2

F1

F3

F2

Figure 8. Fuse Holder and Fuses

RESULTS:

1. Replace blown fuse(s) as needed.

teSt 35 – check n1 and n2 WirinG

DISCUSSION:
A shorted Wire N1 or N2 to ground can cause fuse F1
or F2 to blow.

PROCEDURE:

1. On the generator panel, set the AUTO-OFF-MANUAL

switch to OFF.

2. Turn off the utility power supply to the transfer switch,

using whatever means provided.

3. Remove fuses F1, F2, and F3 from the fuse holder (see

Figure 7).

4. Remove the generator control panel cover. Disconnect

the N1/N2 connector that supplies the printed circuit

board located in the control panel (see Figure 6).

5. Set VOM to measure resistance.

6. Connect the positive meter test lead to Wire N1 at the

terminal block in the control panel.

a. Connect the negative meter lead to the ground

lug. INFINITY should be measured.

b. Connect the negative meter lead to Wire

23 at the terminal strip. INFINITY should be
measured.

c. Connect the negative meter lead to Wire 15B at

the terminal strip. INFINITY should be measured.

d. Connect the negative meter lead to Wire 0 at the

terminal strip. INFINITY should be measured.

e. Connect the negative meter lead to Wire N2 at the

terminal block. INFINITY should be measured.

f. Connect the negative meter lead to the neutral

connection. INFINITY should be measured.

7. Connect the positive meter test lead to Wire N2 at the

terminal block in the control panel.

a. Connect the negative meter lead to the ground

lug. INFINITY should be measured.

b. Connect the negative meter lead to Wire 23 at

the terminal strip. INFINITY should be measured.

c. Connect the negative meter lead to Wire 15B at

the terminal strip. INFINITY should be measured.

d. Connect the negative meter lead to Wire

0 at the terminal strip. INFINITY should be
measured.

e. Connect the negative meter lead to the neutral

connection. INFINITY should be measured.

RESULTS:
If a short is indicated in Step 6 or Step 7, repair wiring
and re-test.

teSt 36 – check n1 and n2 VoltaGe

DISCUSSION:
Loss of utility source voltage to the generator will initi-
ate a startup and transfer by the generator. Testing at
the control panel terminal block will divide the system
in two, thereby reducing troubleshooting time.

PROCEDURE:

1. Set the AUTO-OFF-MANUAL switch to OFF.
2. Set a VOM to measure AC voltage.
3. See Figure 9. Connect one test lead to Wire N1 at the

terminal block in the generator control panel. Connect

the other test lead to Wire N2. Utility line-to-line voltage

should be measured.

RESULTS:
Refer to Flow Chart

Page 83

TRANSFER SWITCH

sEctioN 3.4

DiaGNostic tEsts

Part 3