9 hose carrier assembly - four section boom, 1 hose carrier assembly removal, Hose carrier assembly - four section boom – JLG 4013PS Service Manual User Manual

Page 54: Hose carrier assembly removal

Advertising
background image

Boom

3-22

3508PS, 3509PS, 3512PS, 3513PS, 4008PS, 4009PS, 4012PS, 4013PS, 4017PS, 40.8, 40.9

4. Start the machine and extend and retract the boom

sections two or three times. Fully retract the boom
and measure the distance between the boom
sections.

5. If the measurements are within the tolerance, tighten

the locknuts on the chain clevises. If more
adjustment is needed, repeat procedure until the
proper boom section dimensions is achieved.

6. With the boom sections within the proper tolerance,

start the machine, lower the outriggers if necessary
and extend the boom to maximum extension.

7. Shut the machine off and measure the distance

between the top of both extend chains and the
bottom of the second and third boom sections at the
center of each boom section.

8. The distance between the top of the extend chains

and the bottom of the second boom section should
be approximately 180 mm (7 in). The distance
between the top of the extend chains and the bottom
of the third boom section should be approximately
120 mm (4.75 in).

Note: If the second boom section to the third boom
section separation distance cannot be achieved, contact
the local JLG distributor or the JLG Service Department.

3.9

HOSE CARRIER ASSEMBLY - FOUR
SECTION BOOM

3.9.1

Hose Carrier Assembly Removal

1. Remove any attachment from the quick switch

assembly. (Refer to Section 3.11.1, “Connecting with
a Mechanical Quick Switch Device.”
)

2. Park the machine on a hard, level surface. Be sure

there is enough room in front and rear of the
machine to extend the boom sections and to be able
to removed the hose carrier from the rear of the
boom assembly.

3. Fully extend the boom and raise the boom to a

horizontal position. Place the transmission control
lever in (N) NEUTRAL, engage the park brake
switch.

4. Retract the boom until the rear hose carrier

mounting bolts on the fourth boom section are
accessible through each side of the third boom
section access holes. Shut off the machine and
remove the bolts.

5. Start the machine and retract the boom until the

middle set of hose carrier bolts on the fourth boom
section are accessible through the third boom
section access holes. Shut the engine OFF and
remove the bolts.

6. Start the engine and retract the boom until the front

set of hose carrier bolts on the fourth boom section
are just in front of the front of the third boom section.
Shut the engine OFF and remove the bolts.

7. Start the engine and slowly retract the boom

sections completely.

8. Shut the engine OFF and place a Do Not Operate

Tag on both the ignition key switch and the steering
wheel, stating that the machine should not be
operated.

9. Relieve any trapped pressure in the tilt hydraulic

system by using the handle provided or a 9mm
wrench and move the double nut on the side of the
main control valve tilt section back and forth. Repeat
on the auxiliary valve section.

10. Locate the two hoses attached to the barrel of the tilt

cylinder inside the boomhead.

MZ1220

120mm - 4.75in

180mm - 7in

Advertising