Commissioning

Before switching on

6

l

33

EDS82ZAFPC010 EN 4.0

6

Commissioning

During commissioning, system−dependent data as e.g. motor parameters, operating
parameters, responses and parameters for fieldbus communication are selected for the
controller.

In Lenze devices, this is done via codes. The codes are stored in numerically ascending order
in the Lenze controllers and in the plugged−in communication/function modules.

In addition to these configuration codes, there are codes for diagnosing and monitoring
the bus devices.

6.1

Before switching on

(

Stop!

Before switching on the standard device with the function module for the first
time, check...

ƒ

the entire wiring for completeness, short circuit, and earth fault.

ƒ

whether the integrated bus terminating resistor is activated at the first and
last physical node (

40).