Commissioning

Connecting the mains voltage

6

l

42

EDS82ZAFPC010 EN 4.0

6.6

Connecting the mains voltage

)

Note!

If the external voltage supply of the function module is used, the supply must
be switched on as well.

ƒ

The standard device will be ready for operation approx. 1 s after switching on the
supply voltage.

ƒ

Controller inhibit is active.

ƒ

The green LED at the front of the function module is lit (only visible in the case of the
8200 vector frequency inverter).

Protection against uncontrolled start−up

)

Note!

Establishing communication
For establishing communication via an externally supplied function module,
the standard device must be switched on as well.

ƒ

After communication has been established, the externally supplied module
is independent of the power on/off state of the standard device.

Protection against uncontrolled start−up
After a fault (e.g. short−term mains failure), a restart of the drive is not always
wanted and − in some cases − even not allowed.
The restart behaviour of the controller can be set in C0142:

ƒ

C0142 = 0 (Lenze setting)
– The controller remains inhibited (even if the fault is no longer active).
– The drive starts in a controlled mode by explicitly enabling the controller:

LOW−HIGH edge at terminal 28 (CINH)

ƒ

C0142 = 1
– An uncontrolled restart of the drive is possible.