Cabinet handling instructions – Rockwell Automation 7712 OneGear Motor Control Center FVNR Starter (7.2 kV) User Manual

Page 10

Advertising
background image

3-2

Transportation and Handling

7712-IN001B-EN-P – June 2013

Cabinet Handling Instructions

When lifting the Bulletin 7712 OneGear™ cabinet, the lifting instructions
specifi ed below must be followed.

Overhead Lifting Method

1. Verify that the front/back lifting channels and the middle cosmetic

channels are all installed and that the connecting hardware is tightened
to the cabinet.

2. Verify that the four (4) lifting clips have corresponding internal lifting

clips installed and connected. Lifting clip holes are 30 mm.

3. Figure 3.1 is only for lifting demonstration purpose. The lifting parts

may be different depending on customers’ decision and availability
of the lifting hardware. Verify shipping weight and capacity of lifting
equipment.

4. As shown in Figure 3.1, the angle between the slings and horizontal

must be 45° or more (70° is ideal).

5. The centre to centre distance of the two lifting points of the lifting

angle or beam is to be 882 mm +/- 150 mm (34” +/- 6.0”).

Figure 3.1 – Overhead Lifting of Motor Control Center