4 - equipment installation, Equipment installation, Chapter – Rockwell Automation 7712 OneGear Motor Control Center FVNR Starter (7.2 kV) User Manual
Page 13
Advertising
![background image](/manuals/580586/13/background.png)
Equipment
Installation
Before joining to adjacent equipment, it is necessary to remove the lifting
angles, spacer, washer and bolt.
Figure 4.1 – Removal of Lifting Bracket
Chapter
4
7712-IN001B-EN-P – June 2013
Spacer, Washer
and Bolt
(2) Lifting Angles
4.1
Removal of Overhead
Lifting
Brackets
and
Channels