Rockwell Automation 7712 OneGear Motor Control Center FVNR Starter (7.2 kV) User Manual

Page 40

Advertising
background image

5-2

OneGear™ Standard Plenum Assembly Procedure

7712-IN001B-EN-P – June 2013

3. Install the switchgear gas duct per manufacturer’s instructions

(e.g. ABB UniGear type ZS1 – Standard Gas Duct Assembling Procedure).

4. Locate the ABB connecting adapter plate (81023-965-51/52) for

connecting to the switchgear using M8 hardware (see Figure 5.2a).

Figure 5.2a – Attaching adapter plate to switchgear

5. Locate the front inner bracket (81021-958-51) for connecting to

switchgear temporarily using M8 hardware (see Figure 5.2b).

Figure 5.2b – Attaching front inner bracket

6. Apply gasket to the bottom fl ange of all front and rear assemblies (refer

to Figure 5.3).

Advertising