Figure 22: subordinated – BECKHOFF ET9300 User Manual

Page 62

Advertising
background image

60

Application Note ET9300

Cycles). The relation between Sync0 and the bus cycle is configured by the ESI
element:CycleTimeSync0@Factor.

Possible Outputs valid

Possible Inputs latch

Calc and Copy

Time

(0x1C32.6)

Delay Time

(0x1C32.9)

Calc and Copy

Time

(0x1C33.6)

Delay Time

(0x1C33.9)

Sync0

Sync1

PDO_OutputMapping()

SM2 Event

PDO_InputMapping()

Sync0 Cycle Time

(0x1C32.10/0x1C33.10)

Cycle Time (0x1C32.02/0x1C33.02)

Sync0

Sync1

Start Input Latch

ECAT_Application()

Sync0

ECAT_Application()

Sync0

ECAT_Application()

Sync0

ECAT_Application()

SM2 Event

Figure 22: Subordinated Cycles

Subordinated Cycles synchronization parameter:
Sync Activation Register (0x981): Bit0, Bit1, Bit2 = 1
Sync0Cycle Time (0x9A0:0x9A3) < Sync1Cycle Time (0x9A4:0x9A7)
0x1C32.1 = 3
0x1C33.1 = 3
AL_EVENT_ENABLED = 1