3.3 DRILLING (Cy

c

le 20

0)

3.3 DRILLING (Cycle 200)

Cycle run

1

The TNC positions the tool in the spindle axis at rapid traverse
FMAX to the setup clearance above the workpiece surface.

2

The tool drills to the first plunging depth at the programmed feed
rate F.

3

The TNC returns the tool at FMAX to the setup clearance, dwells
there (if a dwell time was entered), and then moves at FMAX to
the setup clearance above the first plunging depth.

4

The tool then advances with another infeed at the programmed
feed rate F.

5

The TNC repeats this process (2 to 4) until the programmed depth
is reached.

6

The tool is retracted from the hole bottom to the setup clearance
or—if programmed—to the 2nd setup clearance at FMAX.

Please note while programming:

Program a positioning block for the starting point (hole
center) in the working plane with radius compensation R0.

The algebraic sign for the cycle parameter DEPTH
determines the working direction. If you program DEPTH
= 0, the cycle will not be executed.

Danger of collision!

Use the machine parameter displayDepthErr to define
whether, if a positive depth is entered, the TNC should
output an error message (on) or not (off).

Keep in mind that the TNC reverses the calculation for pre-
positioning when a positive depth is entered. This
means that the tool moves at rapid traverse in the tool axis
to setup clearance below the workpiece surface!