4-1 Introduction

The commissioning phase begins upon completion of the mechanical and electrical installation

of the system and is the phase in which the user makes the system ready for operation. The

commissioning process consists of performing the following procedures, which are explained

elsewhere in this section:

• Inspect the Installation

• Check Input and Output Wiring

• Install Analogue Input Signal Conditioners (AISCs)

• Set Jumpers (such as address jumpers and end-of-cable termination jumpers)

• Apply Partial Power

• Load Software and Configure the Controller(s)

• Initial Tests

• Final System Checkout

4-1.1 Inspect the Installation

Referring to Chapters

2

,

3

and

5

, inspect the entire system for correct mechanical, electrical and

network installation. Correct any discrepancies noted. Inspection should include the factors listed

in the following paragraphs, as a minimum.

4-1.1.1 Mechanical Inspection

Ensure that all units and enclosures are free of debris such as dust, metal chips, moisture, etc. That

may have been deposited during installation. Clean as necessary.

• Ensure all covers are properly installed. Exceptions are the CS REM Control Station Module and

MZS REM Multi Zone Station Module, which should be covered by plastic at this time (see

3-4.9

to

3-4.13

).

• Ensure all units and DIN-rails are solidly mounted.

• Check cable ducts. Ensure they are placed so that cables entering and leaving the ducts do not

make overly tight bends.

• Make sure all units are located to provide safe access for operation and maintenance.

• Make sure all units are located where they are not subject to temperature extremes beyond the 0 -

40°C range.

• Make sure all units are located as far as practical from high current or high voltage cables or

sources of RF emissions.

• Ensure if wireless sensors are used that a GEN II WMI wireless module interface (WMI) is connected

to and no further than 500 metres from the Genesis II Direct Digital Controller or MPCII Mid Points

Controller and that each wireless sensor is no further than 20 metres from the WMI.

• Do not install the WMI inside a fully enclosed metal switch board.

To prevent injury to personnel and damage to equipment, all electrical power must be off before starting the

commissioning process this includes power to the Genesis units and power to input and output circuits and

equipment. When working with live power ensure that all electrical safety standards for work on live electrical

systems meet local regulatory requirements. Do not apply power to any unit or circuit until instructed to do so by

procedures in this section.