Safety Tests during operation
62
--------------------WARNING--------------------
THE SELECTED TESTCODES SPECIFY
THAT A FLASH TEST SHOULD BE
PERFORMED.
THIS IS NOT POSSIBLE ON THE
SUPERNOVA XE.
THE FLASH TEST WILL BE SKIPPED.
PRESS THE START KEY TO
CONTINUE.
Safety Tests during operation
The Tester performs self-tests during normal operation. An internal
earth bond test and a low voltage test are performed prior to applying
mains power to any EUT (including Load/Leakage and Touch
Leakage tests). If the internal earth bond test is failed, the following
message will be displayed:-
--------------------WARNING--------------------
INTERNAL RELAY FAULT.
CANNOT PROCEED.
If this message appears, the Supernova XE is faulty and requires
repair.
If the low voltage test fails, then either of the following warnings will
be displayed:-
--------------------WARNING--------------------
APPLIANCE MAY BE SHORT CIRCUIT
PRESS THE ENTER BUTTON IF SAFE
PRESS THE RED BUTTON TO ABORT
--------------------WARNING--------------------
FUSE MAY BE OPEN CIRCUIT OR
PRESS THE ENTER BUTTON IF SAFE
PRESS THE RED BUTTON TO ABORT