3. Electrical Installation

PNEG-1895 V2 Electronic Distributor Control

15

Control Panel Installation Guidelines

The following requirements must be followed when installing and mounting the control panel:

All wiring should be performed by a licensed/qualified electrician in accordance with the National Electric
Code (NEC), state codes and local codes.

Never mount the control panel immediately beside or above heat generating equipment or directly below
water or steam pipes.

The atmosphere surrounding the control panel must be free of combustible vapors, chemical fumes and
corrosive materials.

The control panel must be easily accessible for maintenance and operation.

Mount the control panel on a flat, vertical surface using 1/4" fasteners.

Ensure that the mounting surface is sufficient to support the weight of the control panel.

Rigid conduit connections must be placed either at sides or bottom of the control panel.