Use the sling-rigged method to lift large detectors into a vertical position while they are still crated Use this method

to position while they are still crated Use this method to position large detectors vertically into pipelines

Figure 3: Sling-Rigged Lifting Methods

Do not lift a detector with a forklift by positioning the detector body on the forks, with the flanges extending beyond

the lift This could dent the housing or damage the internal coil assemblies

Never place forklift forks, rigging chains, straps, slings, hooks or other lifting devices inside or through the detector's

flow tube to hoist the unit This could damage the isolating liner

Do not lift detector with forklift

Do not lift or rig lifting devices through detector

Figure 4: Lifting and Rigging Cautions