Commissioning

During commissioning, system-related data such as motor parameters, operating

parameters, responses, and parameters for fieldbus communication are defined for the

controller. For Lenze devices, this is done via the codes.
The codes of the controller and communication are saved non-volatilely as a data set in the

memory module.
In addition to codes for the configuration, there are codes for diagnosing and monitoring

the nodes.



Parameter reference

( 66)

The data from the controller or memory module can only be read in conjunction with the

main voltage supply (400/500 V AC).
During commissioning with 24 V DC, only the information provided by the last two data

words in the digital and analog inputs is valid and readable (see

Configuring process data

( 28)

).

6.1

Before initial switch-on

Stop!

Before the controller is switched on for the first time, the entire wiring must be

checked for completeness, short circuit and earth fault.