Chapter, Chapter chapter 4 4 4 4, System start – Rockwell Automation AADvance Controller System Build User Manual

Page 81: System start system start----up up up up

Advertising
background image


Document: 553632
(ICSTT-RM448_EN_P) Issue: 08:

4-1

This chapter describes a structured approach to the start up of a controller system.
When the checks and module installation and start up is completed successfully, the
system is ready for a Functional Acceptance Test.

In This Chapter

In This Chapter

In This Chapter

In This Chapter

Recommendations to Manage Test Documentation .................................. 4-1
System Physical Design Check ......................................................................... 4-2
Procedure to Verify Build State ...................................................................... 4-2
Procedure to Conduct the Mechanical Inspection ..................................... 4-2
Procedure to Check Ground Bonding .......................................................... 4-2
Procedure to check Power Distribution Integrity ...................................... 4-3
Power Distribution and First Power Up ....................................................... 4-3
Start Up Process ................................................................................................. 4-4
Processor Module Start Up Process .............................................................. 4-4
I/O Module Start Up Process .......................................................................... 4-7
ControlFLASH Firmware Upgrades ............................................................. 4-10
Setting Up the Controller IP Address for AADvance Workbench
Communications ............................................................................................... 4-24

Recommendations to Manage Test Documentation

Recommendations to Manage Test Documentation

Recommendations to Manage Test Documentation

Recommendations to Manage Test Documentation

It is important that the system is documented when it is installed and this
documentation is maintained throughout the testing process system.

1)

Obtain these items of documentation:

I/O wiring database with checklist

Complete set of drawings

Bill of materials

2)

Ensure that each item of documentation is the latest issue.

Mark each item as 'Test Copy'.

3)

Create a system activity log book and ensure the log book accompanies the system

into test.

Allocate an entry number for each test and record each test against its number
in the log book.

If, during functional tests, the system does not behave as expected, record the
problem in the log book. Allocate a new entry and fault number for each
problem.

Chapter

Chapter

Chapter

Chapter 4

4

4

4

System Start

System Start

System Start

System Start----Up

Up

Up

Up