Rockwell Automation 1394 SERCOS Interface Multi-Axis Motion Control System Installation Manual User Manual

Page 72

Advertising
background image

Publication 1394-IN002B-EN-P — February 2004

3-18

Connecting Your 1394 SERCOS Interface System

Wiring Main Input Power

To wire the main input power terminal block:

1. Prepare the incoming three-phase power wires for attachment to

the input power terminals by removing 10 mm (0.375 in.) of
insulation.

2. Route the three-phase power wires (U, V, W, and PE) to your 1394

system module.

3. Connect the system module ground wire from the system module

single point bond bar to the bonded ground bar or bonded
cabinet ground bus on the subpanel (as shown in Figure 3.7). For
more information on bonding, refer to Chapter 1.

4. Open the front door of the system module and locate the 22 kW

system module terminal blocks (refer to Figure 2.2).

5. Insert the incoming power wires into the terminal blocks as

follows and tighten the four terminal block screws.

6. Gently pull on each wire to make sure it does not come out of its

terminal block. Re-insert and tighten any loose wires.

IMPORTANT

Use caution not to nick, cut, or otherwise
damage strands as you remove the insulation.

Insert the wires labeled:

Into the terminal blocks labeled:

U

U

V

V

W

W

Ground

PE

Advertising